2021 · GS Paper 4 · Q9 · 20 marks

An elevated corridor is being constructed to reduce traffic congestion in the capital of a particular state. You have been selected as project manager of this prestigious project on your professional competence and experience. The deadline is to complete the project in next two years by 30 June, 2021, since this project is to be inaugurated by the Chief Minister before the elections are announced in the second week of July 2021. While carrying out the surprise inspection by inspecting team, a minor crack was noticed in one of the piers of the elevated corridor possibly due to poor material used. You immediately informed the chief engineer and stopped further work. It was assessed by you that minimum three piers of the elevated corridor have to be demolished and reconstructed. But this process will delay the project minimum by four to six months. But the chief engineer overruled the observation of inspecting team on the ground that it was a minor crack which will not in any way impact the strength and durability of the bridge. He ordered you to overlook the observation of inspecting team and continue working with same speed and tempo. He informed you that the minister does not want any delay as he wants the Chief Minister to inaugurate the elevated corridor before the elections are declared. Also informed you that the contractor is far relative of the minister and he wants him to finish the project. He also gave you hint that your further promotion as additional chief engineer is under consideration with the ministry. However, you strongly felt that the minor crack in the pier of the elevated corridor will adversely affect the health and life of the bridge and therefore it will be very dangerous not to repair the elevated corridor. (a) Under the given conditions, what are the options available to you as a project manager? (b) What are the ethical dilemmas being faced by the project manager? (c) What are the professional challenges likely to be faced by the project manager and his response to overcome such challenges? (d) What can be the consequences of overlooking the observation raised by the inspecting team?

In short

The project manager should record his dissent, seek written orders, get an independent structural test and rebuild the three piers on a crashed schedule rather than overlook the crack. A hurried reopening without a fitness certificate lay behind the Morbi bridge collapse of October 2022, which killed 135 people.

Model answer

Ghissu Editorial · Verified 4 Oct 2026

Introduction
When the Morbi bridge collapsed in October 2022, killing 135 people, a hurried reopening without a fitness certificate, not engineering, was to blame. This case asks whether an inauguration may outrank a structure's life.
(a) Options Available to the Project Manager
•

(i) CAPITULATE [Procedural-Evasive]

Obeying the Chief Engineer meets the deadline but is Conscience Laundering through Hierarchy.

•

(ii) CONFRONT [Empathetic-Humanitarian]

Going to the media is a Lone-Rebel Reading.

•

(iii) EVADE [Procedural-Evasive]

Seeking a transfer is Moral Escapism.

•

(iv) COMPROMISE [Compromised-Hybrid]

A cosmetic patch hides a material defect.

•

(v) RECONCILE ✓ [Balanced]

Record dissent, seek written orders, get an independent test, rebuild on a crashed schedule (recommended).

Justification:
Gandhi's Talisman: the poorest commuter riding over that pier makes a cosmetic fix indefensible.
(b) Ethical Dilemmas Faced by the Project Manager
The core dilemma is Public Safety vs Timely Delivery, with Professional Integrity vs Obedience and Career vs Duty of Care; the minister's relative as contractor is a Conflict of Interest.
(c) Professional Challenges and Response
•

Overruled by superior

Record dissent and act on written orders, as T.S.R. Subramanian (2013) [case] advised.

•

Deadline and career pressure

Offer a crashed schedule; Durga Shakti Nagpal (2013) [officer] was reinstated after a documented stand.

(d) Consequences of Overlooking the Observation
•

Lives and liability

Collapses like Varanasi (2018) [current event] kill, and negligence invites Section 106 BNS prosecution.

•

Cost and trust

Later retrofitting costs more and teaches that warnings are negotiable.

Conclusion
An inauguration can be rescheduled; a collapse cannot be undone, so safety must be designed into the process.

This model answer is indicative and the model can make mistakes; please verify key facts independently.

Hand-drawn diagram: Public Safety vs Timely Delivery. Public Safety vs Timely Delivery. Venn diagram: Public Safety, Timely Delivery; overlap: Test, rebuild, crash the schedule
Diagram: Public Safety vs Timely Delivery

Practise this question

  1. 1Get the answer sheet

    Sized for this question.

  2. 2Write your answer

    Timed, by hand.

  3. 3Get it marked

    Your score and what to fix.

Share this questionWhatsAppTelegramXLinkedIn

This chapter in the exam

Public Sector and PSU Dilemmas4 questions

Asked in 4 of 14 sittings since 2013

2013
1
2014
–
2015
–
2016
–
2017
–
2018
–
2019
–
2020
–
2021
1
2022
–
2023
1
2024
–
2025
1
2026
–

All 4 questions, sorted by sub-topic, with model answers and practice.

Question from the official UPSC Civil Services (Main) Examination 2021 paper. Answer written by Ghissu's engine and checked against our editorial standards. Found an error? Tell us and we correct it within 48 hours.

Ghissu

OUTWORK·
OUTTHINK·
MASTER THE SYSTEM·
OUTWORK·
OUTTHINK·
MASTER THE SYSTEM·
OUTWORK·
OUTTHINK·
MASTER THE SYSTEM·
OUTWORK·
OUTTHINK·
MASTER THE SYSTEM·
OUTWORK·
OUTTHINK·
MASTER THE SYSTEM·
OUTWORK·
OUTTHINK·
MASTER THE SYSTEM·
OUTWORK·
OUTTHINK·
MASTER THE SYSTEM·
OUTWORK·
OUTTHINK·
MASTER THE SYSTEM·